Building Inspections
Inspection Request:
Contact Melonie McLendon, (706) 595-5355, to schedule an inspection. Inspections should be called in at least 48 hours in advance.
New House:
- Footer/Slab inspection required before any concrete is poured
- Rebar and grade stakes in place
- Step Downs in place
- Plumbing in Slab in place with test (if required)
- Vapor Barrier installed
Rough-in inspection required before any insulation or sheet rock installed
- Framing complete
- Electrical rough in complete
- Plumbing rough in complete
- HVAC rough in complete
Electrical Release
- Electrical 100% complete
- Drain Lines connected to sewer/septic system
- HVAC disconnects installed
Certificate of Occupancy Inspection:
- All work 100% complete
- Address displayed
Mobile Home
If available, the mobile home set up manual must be on site.
1st Inspection:
- Inside must be accessible
- Footers Piers and anchoring in place
- Electrical installed
- Plumbing installed
- HVAC Duct installed
2nd Inspection:
- Masonry Completed
- Steps and Landings Completed
- HVAC Completed
- Address Displayed
After these steps are completed the power will be released.